Hike & Bike Trails Type B Development

Hike & Bike Trails Type B Development

Hike and Bike Trail Steering Committee

Rae Sinor – City Council | Tommy Ginn – City Council | James Stokes – City Manager | Gary Jackson – Assistant City Manager | Charlie Sandberg – Parks and Recreation Director | Jacob Zuniga – Assistant Parks and Recreation Director | Tiffany McGallian – Parks Operations Supervisor | Brent Costlow – Assistant Public Works Director | Jeff Lawther – Deer Park Community Development Member | Laura Hicks - Deer Park Community Development Member | Eric Ripley – Deer Park Parks and Recreation Commission Member | Sherry Redwine - Deer Park Parks and Recreation Commission Member

Hike and Bike Trails – This is one of the seven projects that was approved at a Special Election for Type B Economic Development Sales and Use Tax Proposition in May 2015. Burditt Consultants LLC has been contracted to administer architectural services for the construction phase. The initial trail will be a 1.04-mile trail that connects East X Street to East P Street and connects Tiffany Amber Park, Wynfield Park, and Runningbrook Park by way of existing sidewalks. 

Recent update on this new trail system.

  • November 2, 2021 – City Council Awarding the “Request for competitive sealed proposals for the Phase 1 AUT 21-050 Hike and Bike Trail Project” from X Street to P Street to Moran Construction, LLC.
  • December 2021 – Front End Documents completed from Moran Construction for the Project.
  • April –June of 2022 – Moran Construction continues work on the Type B hike and bike project with an anticipated completion date of July 2022.
  • Several change orders were requested during this project for additional bollards and additional concrete work.

Hike and Bike Phase 1 Smaller

Phase 2 Hike and Bike Trail Improvements Site Feasibility Study for Proposed Alignments – Preliminary Observations

Phase 1 - Hike and Bike Trail